In-brief analysis

March 11, 2025

Data source: U.S. Energy Information Administration, Liquefaction Capacity File; trade press
Note: Commissioning refers to the stage in LNG export facility development from the start of LNG exports to full production capacity. Bcf/d=billion cubic feet per day; LNG=liquefied natural gas

In February 2025, Corpus Christi Stage 3, an expansion of the existing Corpus Christi liquefied natural gas (LNG) export facility, produced its first LNG cargo, according to the developer Cheniere Energy. Corpus Christ Stage 3 started producing LNG in December 2024. The start of LNG exports from Corpus Christi Stage 3 follows shortly after the start of exports from another U.S. LNG export facility—Plaquemines LNG Phase 1—also in December.

The Corpus Christi Stage 3 expansion facility, located next to the existing Corpus Christi LNG terminal in San Patricio County, Texas, consists